The CIPE has approved of Harbour the definitive project "Hub of Ravenna"
Within the summer the contest ban, in order to activate the work in 2019
February 28, 2018
Today the Interministerial Committee for Economic Planning (CIPE) has approved of Harbour the definitive project "Hub of Ravenna", ravvennate development plan of the port that in its first phase previews the deepening of the backdrops in long outer harbor and all the Candiano Channel to -12,5 meters, the realization of a new dock for terminal container of the length of beyond thousand linear meters, the structural adaptation to the antiseismic norm and the new backdrops of beyond 6.500 meters of existing docks and the realization of destined areas to the logistics in harbour within for about 200 hectares, areas that will be connected to the railway net for traffic goods.
The green light today's on December 15, 2017 concludes iter autorizzativo of the project delivered to the Ministry of Infrastructures and the Transports 18th September and fired with positive opinion from the Higher council of the Public works.
The investment previewed for the first phase of the project is of 235 million euros. The Authority of Harbour System of Mare Adriatico Centro-Settentrionale, expressing satisfaction for the judgment of the CIPE and thanking for the carried out job the Emilia Romagna Region, the Municipality of Ravenna, the Provveditorato to the Public works and all those who have allowed to reach this goal, has remembered that the project will contribute to activate other investments, also of private subjects, for ulterior 300 million euros, that they will comprise the realization of the system of treatment of the materials of turns out of the escavo, private investments in the logistics, the ulterior deepening of the Candiano Channel until 14,50 meters, previewed in the second phase of the project, and a coastal warehouse of GNL.
The harbour agency has remembered moreover that the project, for the importance which strategic investment for the European logistic net, has obtained a contribution from the European Union of 37 million euros, than is gone to add to 60 million already allocated from the CIPE, to 120 deriving from a mortgage of the European Investment Bank and to resources own of the Authority of Harbour System, and that of it they guarantee the cover financial institution.
The AdSP has specified that the phase of performance of the project previews that within the summer is published the contest ban, than within the year is arrived to the definitive award and in the 2019 they begin the work.
- Via Raffaele Paolucci 17r/19r - 16129 Genoa - ITALY
phone: +39.010.2462122, fax: +39.010.2516768, e-mail
VAT number: 03532950106
Press Reg.: nr 33/96 Genoa Court
Editor in chief: Bruno Bellio No part may be reproduced without the express permission of the publisher