By July 1,500 meters of dock of the Polisettoriale Pier of Taranto will be operating
To May 2018 the dredging work will finish
May 19, 2017
Yesterday the Authority of Harbour System of the Ionian Sea has taken in anticipated delivery the first phase of the work of requalification of the Polisettoriale Pier. Draft of the first 600 linear meters of dock that are completed to August 2016 and are delivered yesterday after the static test of the structures. The completion of remaining the 600 meters of dock is previewed for next the 5 june and the delivery in the course of the next month after the execution of the static test.
The AdSP of the Ionian Sea has emphasized that, therefore, within the July end the modernization works will be completed and will be operating 1,500 meters of dock and the rear large squares, exactly the areas consented in concession to the terminalista operating precedence, that is the Taranto Container Terminal (TCT), society that - mail in liquidation - had given back the areas to harbour authority in September 2015 ( on 29 September 2015).
Moreover the AdSP has remembered that they are under realization the participations for the realization of the overwhelmed case of in widening of V Sporgente and the dredging of the dock of mooring of the Polisettoriale Pier that will carry the backdrops to the depth of -16,5 meters for the first 1,200 meters and -15,0 meters for the remaining part. These work will finish already to May 2018 with the possibility to have a part of the dock to -16,5 meters in the first months of the year.
- Via Raffaele Paolucci 17r/19r - 16129 Genoa - ITALY
phone: +39.010.2462122, fax: +39.010.2516768, e-mail
VAT number: 03532950106
Press Reg.: nr 33/96 Genoa Court
Editor in chief: Bruno Bellio No part may be reproduced without the express permission of the publisher