Today the installation of the first four of eight was completed
spans of the new railway bridge over the Western Industrial Canal at
Porto Marghera, a project with a total value of about 28 million
euro that will allow the fitting to be directly connected
port railway with Marghera Scalo station, avoiding the
transit to Mestre station.
Structural elements, for a total weight exceeding
455 tons, were produced in Porto Viro (Rovigo) and
transported by water to Porto Marghera, aboard a barge
with a tugboat with a load capacity of 1,795
tons. Transport started from the assembly site
of Ca' Cappello, it traveled the Po Canal of Brondolo and the Canal of
Cavanella d'Adige, entering the lagoon through Chioggia to
finally reaching the West Industrial Canal.
The intervention involves the construction of a deck in
steel, approximately 158 meters long in total, with the completion of the
works scheduled for 2027.