Yesterday the board of directors of the Authority
Port of Barcelona has decided to launch a tender for
the granting of a concession related to design,
construction, management, and maintenance of the supply service of
electricity to ships through connection systems with the
terrestrial power grid that allow vessels to
Turn off the engines during the berth stop.
The call for proposals provides for the establishment of a single concessionary company,
in which the Port Authority will hold a stake
30%, according to a public-private partnership model. With
This participation aims to ensure an active role in the
governance of a service that is strategic for the airport
Catalan, ensuring alignment with development objectives
and electrification of the port, as well as in coordinating
Onshore Power Supply infrastructures with planning
general of the port.
The new company will have the
task of continuing the work started in recent years and
will be responsible for completing the different components
of the electrical infrastructure: transformer stations and
frequency conversion, power grid, connection systems for
ships, cable management systems, as well as systems of
control and management. In addition to infrastructure development, the
the company will also be responsible for its management and
maintenance.
The port authority specified that the creation of this
The company is part of the port's energy transition plan
which foresees a total investment of 1.7 billion euros, of
of which 780 million come from public funds and 920 million from
private capital, with a central element being the plan
"Nexigen" dedicated to platform electrification.
With a total investment of 215 million euros, the Nexigen plan
has already started the supply of electricity to
container ships and ferries. To date, the port has completed or is
carrying out projects worth 65 million euros within the
of the Nexigen plan and the new company will take charge
of the remaining 150 million euros of investments. According to the
forecasts, the first OPS systems at cruise terminals will be
installed by 2027, while the completion of the remaining
infrastructure and OPS systems in all terminals for
containers, ferries, and cruises will take place by 2030.