The Port System Authority of the Sea of Sicily
Orientale announced that the Court of Appeal of Catania has upheld
the entity's appeal in the complex case related to the works of
upgrading of the commercial quay of the port of Augusta and to the
supply of two large gantry cranes for handling
container. The outcome of the first instance was therefore overturned
in 2024, in fact, the court had condemned the AdSP
to pay about six million euros to the contracting company (the
Stable Consortium of Values). The second instance judges today have
the verdict overturned: the AdSP not only will not have to pay a
euros, but obtained the Consortium's order to compensate the entity
port about 10.7 million for damages suffered and a further 1.8 million for
security bond that must be paid by the company
Elite Insurance Company, amounts to be added
interest, revaluation, and legal expenses.
The AdSP recalled that the dispute arises from the contract for
over 30 million euros awarded in 2013. In 2016, during the
Leak tests carried out on the metal structures of the two new
crane, much higher pressures and times were applied
to those foreseen by the project, causing permanent deformations and
irreparable to the machinery. Following the halt to the works and the
the company's refusal to restore it, in February 2018
the Port System Authority had declared the
contract for serious breach, thus starting the long arm of
legal iron. While at first instance the court held that
the fault for the damages fell exclusively on the management of the
works, thus ruling against the AdSP for having dissolved the
contract, the Court of Appeal accepted the defense line brought
carried out by the body with the support of the District Attorney's Office of the
State of Catania. The judges in fact ruled that
the contractor (Consorzio Valori) and the construction company (Maeg
Construction), as highly qualified operators present in
shipyard, had the precise duty to report the obvious error
in pressure tests and oppose their execution. No
having done so, and having then refused to repair the damages, they
were declared jointly liable together with the management of the
works (RPA Srl). Consequently, the termination of the contract
decided by the AdSP in 2018 was fully declared
legitimate.
Finally, recalling that in July 2024 a new
contract for disassembly, repair, and reassembly of the two
crane on the commercial quay, the AdSP pointed out that such
strategic intervention has made it possible to safeguard funding
community PON and to soon return to the port port of Augsburg
its full operational capacity.