Awarded the tender for the redevelopment of the waterfront of Marina di Carrara
Works awarded to R.C.M. Costruzioni di Sarno
January 11, 2022
The contractual deadline for the conclusion of the work is established in 18 months. The most significant intervention consists of in the creation of a long path that will develop above the wave wall of the pier and which represents the most significant of the entire waterfront project, not only for the size, 870 meters long by five wide, but especially for the panoramic aspect, with its views of the sea open and on the port and with the background of the Apuan Alps.
In addition, the redevelopment of the ground area is planned at the root of the overflow pier and the creation of a new square on the sea at the elbow of the pier. The areas in land will be enhanced through paths made of dunes with native vegetation, cliffs, gentle slopes.
The economic investment for the realization of the project amounts to almost 13.9 million euros, of which 8.6 million from the PNRR - Supplementary fund (Decree-Law 59/2021) and 5.3 million from the Tuscany Region.
- Via Raffaele Paolucci 17r/19r - 16129 Genoa - ITALY
phone: +39.010.2462122, fax: +39.010.2516768, e-mail
VAT number: 03532950106
Press Reg.: nr 33/96 Genoa Court
Editor in chief: Bruno Bellio No part may be reproduced without the express permission of the publisher