Signed the contract for Phase 2 of the overturning at sea of the Fincantieri shipyard in Genoa
The works have a value of 338.7 million euros
March 11, 2022
The Port System Authority of the Western Ligurian Sea signed with the Consorzio Stabile Grandi Lavori, agent of the RTI established with Consorzio Integra Società Cooperativa and Trevi Spa, the contract for Phase 2 of the overturning of Fincantieri, project for the construction of new areas subtracted to the sea for the expansion of the group's shipyard navalmeccanico in Sestri Ponente, in the port of Genoa. The institution port has specified that the act starts the phase of executive design with the prospect of being able to start the preliminary construction site activities in the spring having already almost completed all the surveys and preparatory surveys.
"With the signing of the contract - underlined the president of the AdSP, Paolo Emilio Signorini - we get to the heart of it of the design and execution of a work of great importance for the Genoese naval industry sector that represents an excellence on the international scene and an economic resource and important employment for the port and the territory. Together with the other 29 works of the Extraordinary Program, of which over 80% already built or soon to start, consolidate and increase leaderhip of the first Italian port'.
The works, worth 338.7 million euros, include the expansion of industrial areas and the construction of a new 440-meter super basin that will also allow construction of large ships. In addition, it will be improved accessibility by land with the displacement of the line railway upstream.
- Via Raffaele Paolucci 17r/19r - 16129 Genoa - ITALY
phone: +39.010.2462122, fax: +39.010.2516768, e-mail
VAT number: 03532950106
Press Reg.: nr 33/96 Genoa Court
Editor in chief: Bruno Bellio No part may be reproduced without the express permission of the publisher