Adjudicated to the Astaldi the work of dredging in dock Polisettoriale Pier in the port of Taranto
the economic offer of the company has been pairs to 51,87 million euros more 279 thousand euros for the performance of the safety plans
November 28, 2014
Today the Harbour Authority of Taranto has adjudicated to the Astaldi enterprise of Rome the work of dredging of 2,3 million cubic metres of sediments in dock Polisettoriale Pier and of the relative bathtub of control mud in area adjacent with fifth it jut of the apulian port.
Remembering that made up of contest, to which 11 national and communitarian single competitors and/or in ATI have participated, a definitive project for 72,18 million euros was placed of which 279 thousand euros for inherent burdens the performance of the safety plans, the harbour agency has announced that the economic offer of Astaldi has been pairs to 51,87 million euros more 279 thousand euros for the performance of the safety plans. Moreover the time offered for the execution of the work is pairs to 327 solar days on 670 days previewed in project place made up of contest.
Besides the infrastructural work of deepening from -14,0 to -16,5 meters of the backdrops of the dock of the Polisettoriale Pier, the participation will realize the reclamation of sediments contaminated in the harbour basin.
The Harbour Authority has specified moreover that the contest has afforded to select also the best ones offered under the technical point of view and that the Astaldi winner has offered to realize the fat edge of the bathtub of control of the mud of dredging with metallic palancolato of large suitable diameter for the future operation to harbour dock; also the overwhelmed one in bathtub, realized with coming sediments from the dredgings, will be stabilized draining waters to the aim of its uses end as new harbour large square.
Shortly Astaldi will start the executive planning of the propedeutica participation at the beginning of the work. Within October 2015 the completion of a first suitable lottery of work for it is previewed uses by the terminalista Taranto Container Terminal (TCT).
The agency has remembered that the job adjudicated to the Astaldi is complementary to the job, under execution, already contracted out for the requalification of the dock of the Polisettoriale Pier to the aim of the deepening of the backdrops of 2,5 meters.
- Via Raffaele Paolucci 17r/19r - 16129 Genoa - ITALY
phone: +39.010.2462122, fax: +39.010.2516768, e-mail
VAT number: 03532950106
Press Reg.: nr 33/96 Genoa Court
Editor in chief: Bruno Bellio No part may be reproduced without the express permission of the publisher