Today in the port of Marina di Carrara the
installation of the metal structure of the new railway bridge
which replaces the old railway bridge over the Carrione and will be
followed by the displacement of the current railway towards the sea, which
will reconnect to the existing tracks within the station
port area. The works for the modification of the railway route are
already underway and will reach their peak in August,
in which the transport of goods by train is usually interrupted.
At the beginning of next September, once the
new railway line, it will be possible to proceed with demolition
the adjacent old bridge, which will make way for the new
access road to the port and the walkway relating to the cycle path
Tyrrhenian Sea. Both works will make it possible to reach the complete
activation, by June 2027, of the new eastern gate of the
port, through which all incoming and outgoing goods will pass
from the airport, including special modules produced by Baker Hughes. In
in this way, Viale Da Verrazzano will be relieved
from the current traffic of trucks heading to the port, and will be able to
be entirely requalified in a similar way to what is currently being carried out.
happening in viale Colombo.
The works relating to the new gate fall under scope 1 of the
project for the redevelopment of the Marina di Carrara waterfront and
represent a total investment of 16.1 million euros,
over 1.9 million euros relating to the railway bridge.
"The launch of the new railway bridge - underlined the
President of the Ligurian Sea Port System Authority
Orientale, Bruno Pisano, on the occasion of the presentation of the work
- marks a decisive turning point in the logistical organization of the port
of Marina di Carrara. With this strategic work for the port and the
city, we are completing the first phase of works that have
committed the institution for 110 million euros, after the integration between the
ports of La Spezia and Marina di Carrara, 77 in recent years, and
which will continue with the construction of dredging and
the lengthening of the Taliercio quay. By June they will be
completed the works of Area 2 of the redevelopment of the
waterfront up to viale XX Settembre. This ideally represents
the first investment plan that could be implemented in
validity of the old Port Master Plan and that by the end of 2027
we count on completing. The entire structure is working with the
maximum commitment so that it can be concluded positively
the process for the approval of the new Port Master Plan, so much so that
awaited by the entire port community and beyond. In that
it will be possible to start the second phase of the
planned investments, to make the port of Marina di Carrara one of the most important
an innovative, sustainable, attractive and competitive airport".
"The new entrance to the east - added the councillor
to the Economic Development of the Municipality of Carrara, Carlo Orlandi - is
a strategic work not only for the port of Marina di Carrara, but also for the
for our entire territory. Thanks to the interventions that is being carried out
by creating the Port System Authority not only
will improve the interface between the port and the coast, but the
The work of the port itself will be more functional and more
Sure. Investing in the port means investing in the growth of the
territory, invest in qualified jobs and in the
development of strategic sectors, which is why we hope that in the future
continue to work and plan the development of the airport.
Carrara, its province and the whole vast area can no longer
wait: there are challenges that need to be taken up and knots
that must be dissolved, first of all that of the new Plan
Port Regulator, an essential tool for planning
the future of the entire Apuan economy".